Petronor Refinery Coke Plant

La Robla Thermal Power Plant Desulfuration Plant
7 February 2020
Biophysical building
12 February 2020

Petronor Refinery Coke Plant

The works were carried out in the following phases:

  • Demolition phase of existing structures and pavements, in order to condition the area to execute the planned work.
  • Excavation phase and earth movements.
  • Phase of implementation of buried services.
  • Phase of execution of the foundations of the offices, canteens and changing rooms of the contracts.
  • Phase of paving and conditioning of new parking and access point to the refinery.
  • HD3 (HYDROSULFURATION Unit): Reactor R2, Compressor C2-C and New Pumps HD3-P3-A/B.
  • S3 (Amine treatment unit, includes: SATELLITE ELECTRICAL SUBSTATION).
  • H4 (hydrogen unit).
  • Electric trench of 30 KV: 2000 ml. From cogeneration to Coke Plant.
  • Utility unit or U3 (acid treatment unit with high sulphur production).
  • Unit VB 3 (vacuum unit): Concrete structure of the tower of the viscosity reducing vacuum unit (TORRE DEL VACUM FLASHER DE VB3).
  • Interconnection rack.

Customer: Petronor – Repsol

Budget: 20.500.000 €

End date: December 2012